Update of Regulated Concepts 2026: 

Everything you need to know

At Audax Renovables we believe in transparency.

Therefore, we want to explain to you in a simple way the changes that the Government and the CNMC (National Commission of Markets and Competition) have applied to the regulated costs of the electricity bill from January 1, 2026.

What has changed?

Your electricity bill depends not only on the energy you consume, but also on a series of costs set by law that affect all consumers equally., regardless of the marketing company or the type of tariff contracted.

Based on the Resolution of December 18, 2025 and the Order TED/1524/2025, From January 1, 2026, these concepts, regulated by the government, They have been updated and you will see them reflected in your supply bill.

Access tolls (ATR)

The Access Tolls (ATR): The prices paid for the use of transport and distribution networks have been updated, both for the contracted power as for the energy consumed.

Consult the following table to find out which ones apply to your rate:

Power
Energy
ATR Power 2026
ATR Energy 2026
Tab Content #3

Capacity payments

The capacity payments  These are values that guarantee the availability of the electrical system.

Capacity payments
ATR Energy 2026

Variation in System Operator Remuneration

Final value of the System Operator Remuneration:

ROS (€/kWh): 0.00020332

Variation of the Social Bonus

Final value of the Remuneration of Social Bonus:

Social Bonus (€ / CUPS year): 6.979247

Variation in excess power and discrimination coefficients per hourly period

The capacity payments  These are values that guarantee the availability of the electrical system.